Back to Work
Today I was again knee deep in change orders. Revisions of estimates and wording. Each change order is a new part of the contract and must be written the same way as the contract language. It's much like code, one can't change much and still make any sense out of the result. Mostly I write change orders about the civil engineering part of the contract, clearing, excavation, asphalt, fencing, lane stripes, traffic medians and the like. The sturctures are done by another engineer across the aisle from me.
The contract will be finished in August 2003, we have nearly 100 change orders presented and their total value is around 10 million dollars.