All windows in place
It's taken a while but all the oak window frames are now in place. There is still a bit of stonework to do around each frame to ensure that they are secure.
The roofer was expected this week but because of the bad weather they should be here at the start of next week. Fortunately they can start on the back putting in the veluxes. That should give me a little more time to finish the window frames and fit the roof timbers.
I've ordered the five windows for upstairs which should be available for collection in two weeks. Once the roofers have finished I can fit the windows and see some real progress.